Clubhouse Interior Progress

by admin

Just a few photos from different areas of the clubhouse. The kitchen is in, the bathrooms are in, the fitness center is finished, a washer & dryer has been installed, and we've mounted a few TV's and brought in some furniture.






Our Fitness Center:




Blacktop Roads & Driveways Finished

by admin

Spring has been fairly wet in Minnesota so far and has made it tough for some of our projects, but we're very happy to see our new asphalt streets and driveways finished. Here you can see the first blacktop roads going down.










Clubhouse Exterior Finished

by admin

We've finished putting up the wood siding on the clubhouse. We also finished pouring the concrete for the walkway and steps to the front entrance.











Clubhouse Exterior

by admin

Our new wood siding & shingles have arrived. We have finished putting all the cedar-shake shingles on the clubhouse. We also have finished putting the wood siding on our gatehouse and are very pleased with the results. The wood siding is a hand-hewn pine scanlog - quite a mouthful, but this siding gives the clubhouse a beautiful hand-finished cabin look which is ideal for our "up north" location.








Here's a close-up of the hand-hewn pine wood siding.





Clubhouse Roof

by admin

We're almost finished with the roof of the clubhouse. We also have all of our windows installed. Next week we will start putting the wood siding on the exterior.











1 2 3 4 5 >>